What retainage does to your books
Retainage is recognised as revenue when earned but is not collectible until the contract conditions are met. It inflates reported profit relative to available cash, and businesses that do not track it separately consistently overestimate their position.
Track it as its own receivable
Retainage receivable should sit apart from trade receivables, with an expected release date per contract. Mixed into general AR it distorts your aging report and makes days sales outstanding meaningless.
The float can be large
A contractor running several million in annual volume at ten percent retainage can have a six-figure balance outstanding at any time, frequently more than their cash position. It is effectively an interest-free loan to customers.
Collecting it
Release usually requires substantial completion, final inspection and lien waivers. The practical failure is nobody owning the process after the crew has left and attention has moved on. A tracked release date with an owner recovers money that otherwise sits for years.
Retainage you hold
If you hold retainage from subcontractors, that is a payable with its own release conditions, and it should be tracked with the same discipline. Netting the two obscures both.